An out-of-control excavator and a dump truck hanging off a cliff reveal safety risks plaguing the mega-project, which faces further cost blowouts and years of delays.
The renewables project's chief executive, Dennis Barnes, received $323,000 in bonus pay on top of his $1.69 million salary ...
Federal Labor hits back at LNP criticism of Snowy 2.0 cost blowouts with a reminder that it was a Coalition government that ...
Australia’s Snowy Hydro 2.0 remains on the government’s books at $8.3bn despite enormous cost blowouts of the project and ...
Workers at Snowy Hydro 2.0 have recorded dozens of detailed complaints about safety and faulty equipment at the pumped hydro scheme amid heightened tensions between unions and the project's builder.
The federal government remains committed to the renewable energy project, which is now two-thirds complete, more than 10 ...
Finance Minister Katy Gallagher has dodged repeated questions about the cost blowouts at Snowy Hydro 2.0 as the project’s price tag soars more than 20 times above its original estimate.
CFMEU officials lodged more than 500 requests to enter worksites around the Snowy Hydro 2.0 project in the past year, with ...
More than 1000 workers will today walk off the job for 24 hours over pay disputes with employer Future Generation Joint ...
TBM Lady Eileen Hudson has completed tunnelling works for the Snowy 2.0 hydroelectric expansion project in Australia after ...
Senior executives at the electricity generator Snowy Hydro were paid big bonuses while costs for a major expansion continued to spiral. Its major expansion Snowy 2.0 has been beset with problems and i ...
Snowy Hydro says the Snowy 2.0 renewable energy project is on track to deliver power by the end of 2028, but is remaining tight-lipped about how much additional money it needs. The project announced ...